A, Band C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?1). 4 days2). 5 days3). 7 days4). 8 days |
| Answer» ANSWER for this QUESTION is 7 DAYS | |