A contract is to be completed in 50 days and 105 men were set to work, each working 8 hour a day. After 25 days, 2/5th of the work is finished. How many additional men should be employed so that the work may be completed on time, each man now working 9 hour a day?1). 342). 363). 354). 37 |
|
Answer» Answer: C) 35 35 is correct answer. According to the formula, |
|