A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier ?1). 1002). 603). 754). None of these

Answer»

it from PREVIOUS YEAR ssc papers, 75 is the RIGHT ANSWER