| 1. |
A contractor undertook to complete a project in 90 days and employed 60 men on it. After 60 days, he found that $\frac{3}{4}$ of the work has already been completed. How many men can he discharge so that the project may be completed exactly on time ?1). 402). 203). 304). 15 |
| Answer» 20 SEEMS CORRECT. | |