A contractor undertook to complete a project in 90 days and employed 60 men on it. After 60 days, he found that $\frac{3}{4}$ of the work has already been completed. How many men can he discharge so that the project may be completed exactly on time ?1). 402). 203). 304). 15

Answer» 20 SEEMS CORRECT.