1.

A contractor undertook to finish a certain work in 124 days and employed 120 men . After 64 days , he found that he had already done $\frac{2}{3}$ of the work. How many men can be dis- charged now so that the work may finish in time ?1). 482). 563). 404). 50

Answer» 56 : SEEMS CORRECT