A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is1). 30 days2). 27 days3). 20 days4). 25 days

Answer» OPTION 1 : SEEMS CORRECT