BurnDown Chart is used to display ______ Choose the correct option from below LIST (1)Capacity of the TEAM members (2)Project PROGRESS (3)AMOUNT of remaining work with respect to time (4)NONE of the above
Answer:-(3)Amount of remaining work with respect to time