1.

Determine the gear load factor if landing weight is 250 unit and average total load during deflection is 550 unit.(a) 2.2(b) 4(c) 4.5(d) 8.9This question was posed to me during an online interview.The doubt is from Landing Gear topic in division Landing Gear and Subsystems of Aircraft Design

Answer»

Right choice is (a) 2.2

Easy explanation: Load FACTOR is GIVEN by,

Load factor N = AVERAGE load/ WEIGHT during LANDING

= 550/250 = 2.2.