Answer»

Work done by 9 men in a day = 1/20 

∴Work done by 1 man in a day for 7.5 hours = (1/20) ÷ 9 = 1/180 

∴ Work done by 1 man in an hour = (1/180) ÷ (7.5) = 1/1350 

Given that 2 men of latter TYPE are equal to 3 men of former type ⇒ 1 man of latter type = 1.5 men of former type. 

∴ Work done by 1 man of latter type in an hour = 1.5 × (1/1350) = 1/900 

∴ Work done by 1 man in 6 hours = 6 × (1/900) = 1/150 

∴ Work done by 12 men in a day working 6 hours/day = 12 × (1/150) = 2/25 

Days REQUIRED to finish the work = 25/2 = 12.5 days.

Work done by 9 men in a day = 1/20 

∴Work done by 1 man in a day for 7.5 hours = (1/20) ÷ 9 = 1/180 

∴ Work done by 1 man in an hour = (1/180) ÷ (7.5) = 1/1350 

Given that 2 men of latter type are equal to 3 men of former type ⇒ 1 man of latter type = 1.5 men of former type. 

∴ Work done by 1 man of latter type in an hour = 1.5 × (1/1350) = 1/900 

∴ Work done by 1 man in 6 hours = 6 × (1/900) = 1/150 

∴ Work done by 12 men in a day working 6 hours/day = 12 × (1/150) = 2/25 

Days required to finish the work = 25/2 = 12.5 days.