Machine P Can Print One Lakh Books In 8 Hours. Machine Q Can Print The Same Number Of Books In 10 Hours While Machine R Can Print The Same In 12 Hours. All The Machines Started Printing At 9 A.m. Machine P Is Stopped At 11 A.m. And The Remaining Two Machines Complete Work. Approximately At What Time Will The Printing Of One Lakh Books Be Completed ? |
|
Answer» <P>WORK done by P in 1 hour = 1/8 Work done by Q in 1 hour = 1/10 Work done by R in 1 hour = 1/12 Work done by P,Q and R in 1 hour = 1/8 + 1/10 + 1/12 = 37/120 Work done by Q and R in 1 hour = 1/10 + 1/12 = 22/120 = 11/60 From 9 am to 11 am, all the machines were OPERATING. Ie, they all operated for 2 hours and work COMPLETED = 2 × (37/120) = 37/60 Pending work = 1- 37/60 = 23/60 Hours taken by Q an R to complete the pending work = (23/60) / (11/60) = 23/11 which is approximately equal to 2 Hence the work will be completed approximately 2 hours after 11 am ; ie around 1 pm Work done by P in 1 hour = 1/8 Work done by Q in 1 hour = 1/10 Work done by R in 1 hour = 1/12 Work done by P,Q and R in 1 hour = 1/8 + 1/10 + 1/12 = 37/120 Work done by Q and R in 1 hour = 1/10 + 1/12 = 22/120 = 11/60 From 9 am to 11 am, all the machines were operating. Ie, they all operated for 2 hours and work completed = 2 × (37/120) = 37/60 Pending work = 1- 37/60 = 23/60 Hours taken by Q an R to complete the pending work = (23/60) / (11/60) = 23/11 which is approximately equal to 2 Hence the work will be completed approximately 2 hours after 11 am ; ie around 1 pm |
|