1.

P Works Twice As Fast As Q. If Q Alone Can Complete A Work In 12 Days, P And Q Can Finish The Work In --- Days

Answer»

WORK done by Q in 1 DAY = 1/12

Work done by P in 1 day = 2 × (1/12) = 1/6

Work done by P and Q in 1 day = 1/12 + 1/6 = ¼

=> P and Q can finish the work in 4 DAYS

Work done by Q in 1 day = 1/12

Work done by P in 1 day = 2 × (1/12) = 1/6

Work done by P and Q in 1 day = 1/12 + 1/6 = ¼

=> P and Q can finish the work in 4 days