P and Q can do a project in 25 and 50 days respectively. In how many days can they complete 18% of the project if they work together?1). 6 days2). 3 days3). 12 days4). 9 days

Answer»

<P>⇒ One - DAY work of P = 1/25

⇒ One - day work of Q = 1/50

⇒ One - day work of both P and Q together = 1/25 + 1/50 = 3/50

TOTAL TIME TAKEN by them = 50/3 days

⇒ Time taken for 18% work = (18/100) × (50/3) = 3 days