1.

P car complete a piece of wark in 3 days. Q takes triple the time taken by P,R takes 4 times that taken by Q and s takes double the time taken by R to complete the same task. They are grouped in two pairs. One of the pairs takes 2(1)/(2) times the taken by the other pair to complete the work. which is the second pair?

Answer»

P,S
R,R
Q,R
Q,S

Solution :(i)Q and R take 9 days 36 days respecrtively to COMPLETE a piece of work
(ii) Let P take x days, Q takes 3x days, R take 12X days and S take 24 x days
(iii) Findthe part of thework done by each perosn, PER day.
(iv) Then check from the option