InterviewSolution
Saved Bookmarks
| 1. |
Work done by ( x + 4) men in (x + 5) days is equal to the work done by (x - 5) men in ( x + 20) days. Then the value of x is1). 202). 253). 304). 15 |
| Answer» RIGHT ANSWER for this QUESTION is OPTION 1 | |