InterviewSolution
Saved Bookmarks
| 1. |
x does $\frac{1}{4}$ of a job in 6 days. y completes rest of the job in 12 days. Then x and y could ccomplete the job together in1). 9 days2). $9\frac{3}{5}$ days3). $8\frac{1}{8}$ days4). $7\frac{1}{3}$ days |
|
Answer» Its very simple QUESTION $9\frac{3}{5}$ days is the CORRECT answer. |
|