39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work? |
| Answer» Let the required number of days be x. Less persons, More days (Indirect Proportion) More working hours per day, Less days (Indirect Proportion) Persons 30 : 39 :: 12 : x Working hours/day 6 : 5 30 x 6 x x = 39 x 5 x 12 x = (39 x 5 x 12) (30 x 6) x = 13. | |