

InterviewSolution
Saved Bookmarks
1. |
For the network shown in the given figure, the expected time for the activity |
Answer» Expected time = (Pessimistic value + 4*most likely value + Optimistic value)/6. 1-2 is 4. 2-3 is 7. 3-4 is 8. | |