Explore topic-wise InterviewSolutions in Civil Engineering.

This section includes InterviewSolutions, each offering curated multiple-choice questions to sharpen your Civil Engineering knowledge and support exam preparation. Choose a topic below to get started.

1.

For the network shown in the given figure, the expected time for the activity

Answer» Expected time = (Pessimistic value + 4*most likely value + Optimistic value)/6. 1-2 is 4. 2-3 is 7. 3-4 is 8.