A Project With Both Schedule Performance Index (spi) And Cost Performance Index (cpi) Of 0.80. The Project Is Currently: |
|
Answer» CPI < 1 = over budget and SPI < 1 = BEHIND SCHEDULE, so the PROJECT is both “behind schedule and over budget”. CPI < 1 = over budget and SPI < 1 = behind schedule, so the project is both “behind schedule and over budget”. |
|