1.

A Project With Both Schedule Performance Index (spi) And Cost Performance Index (cpi) Of 0.80. The Project Is Currently:

Answer»

CPI < 1 = over budget and SPI < 1 = BEHIND SCHEDULE, so the PROJECT is both “behind schedule and over budget”.

CPI < 1 = over budget and SPI < 1 = behind schedule, so the project is both “behind schedule and over budget”.