1.

For The Project With Earned Value (ev) = $300, Actual Cost (ac) = $250 And Planned Value (pv) = $300. The Original Project Budget Is $1000. Assuming The Project Will Continue To Spend Money At The Same Rate, What Is The Estimate At Completion (eac) Of The Project?

Answer»

As the PROJECT will continue to SPEND at the same current rate,

the FORMULA to be used would be:

EAC = BAC/CPI

CPI = EV/AC

EAC = BAC/(EV/AC) = $1000 / ($300/$250) = $833

As the project will continue to spend at the same current rate,

the formula to be used would be:

EAC = BAC/CPI

CPI = EV/AC

EAC = BAC/(EV/AC) = $1000 / ($300/$250) = $833



Discussion

No Comment Found

Related InterviewSolutions