Saved Bookmarks
| 1. |
For The Project With Earned Value (ev) = $300, Actual Cost (ac) = $250 And Planned Value (pv) = $300. The Original Project Budget Is $1000. Assuming The Project Will Continue To Spend Money At The Same Rate, What Is The Estimate At Completion (eac) Of The Project? |
|
Answer» As the PROJECT will continue to SPEND at the same current rate, the FORMULA to be used would be: EAC = BAC/CPI CPI = EV/AC EAC = BAC/(EV/AC) = $1000 / ($300/$250) = $833 As the project will continue to spend at the same current rate, the formula to be used would be: EAC = BAC/CPI CPI = EV/AC EAC = BAC/(EV/AC) = $1000 / ($300/$250) = $833 |
|