A Project With Earned Value (ev) = $250, Actual Cost (ac) = $200 And Planned Value (pv) = $350. What Is The Cost Performance Index (cpi)? |
|
Answer» The FORMULA to be USED to calculate CPI is: CPI = $250 / $200 = 1.25 The formula to be used to calculate CPI is: CPI = EV / AC CPI = $250 / $200 = 1.25 |
|