1.

For The Project With Earned Value (ev) = $360, Actual Cost (ac) = $400 And Both Cost Performance Index (cpi) And Schedule Performance Index (spi) Equal 0.90. The Original Project Budget Is $1,000. Assuming The Remaining Work Will Be Impacted By The Current Cost Performance And Current Schedule Performance, What Is The Estimate At Completion (eac) Of The Project?

Answer»

As the project will be impacted by the CURRENT cost performance and current schedule performance,

the formula would be:

EAC = AC + [(BAC-EV)/(SPI*CPI)]

EAC = $400 + [($1000 – $360) / (0.9 * 0.9)] = $1190

As the project will be impacted by the current cost performance and current schedule performance,

the formula would be:

EAC = AC + [(BAC-EV)/(SPI*CPI)]

EAC = $400 + [($1000 – $360) / (0.9 * 0.9)] = $1190



Discussion

No Comment Found

Related InterviewSolutions