Saved Bookmarks
| 1. |
For The Project With Earned Value (ev) = $360, Actual Cost (ac) = $400 And Both Cost Performance Index (cpi) And Schedule Performance Index (spi) Equal 0.90. The Original Project Budget Is $1,000. Assuming The Remaining Work Will Be Impacted By The Current Cost Performance And Current Schedule Performance, What Is The Estimate At Completion (eac) Of The Project? |
|
Answer» As the project will be impacted by the CURRENT cost performance and current schedule performance, the formula would be: EAC = AC + [(BAC-EV)/(SPI*CPI)] EAC = $400 + [($1000 – $360) / (0.9 * 0.9)] = $1190 As the project will be impacted by the current cost performance and current schedule performance, the formula would be: EAC = AC + [(BAC-EV)/(SPI*CPI)] EAC = $400 + [($1000 – $360) / (0.9 * 0.9)] = $1190 |
|