A Project With Earned Value (ev) = $250, Actual Cost (ac) = $200 And Planned Value (pv) = $350. What Is The Schedule Performance Index (spi)?

Answer»

The formula to be used to CALCULATE SPI is:

SPI = EV / PV

SPI = $250 / $350 = 0.71

The formula to be used to calculate SPI is:

SPI = EV / PV

SPI = $250 / $350 = 0.71