A Project With Earned Value (ev) = $250, Actual Cost (ac) = $200 And Planned Value (pv) = $350. What Is The Schedule Performance Index (spi)? |
|
Answer» The formula to be used to CALCULATE SPI is: SPI = EV / PV SPI = $250 / $350 = 0.71 The formula to be used to calculate SPI is: SPI = EV / PV SPI = $250 / $350 = 0.71 |
|