Saved Bookmarks
| 1. |
For The Project With Earned Value (ev) = $350, Actual Cost (ac) = $300 And Planned Value (pv) = $400. The Original Project Budget Is $1,000. Assuming The Remaining Work Will Be Impacted By The Current Cost Performance And Current Schedule Performance, What Is The Estimate At Completion (eac) Of The Project? |
|
Answer» As the PROJECT will be impacted by the current cost performance and current SCHEDULE performance, the formula would be: EAC = AC + [(BAC-EV)/(SPI*CPI)] SPI = EV / PV = $350 / $400 = 0.875 CPI = EV / AC = $350 / $300 = 1.167 EAC = BAC/(EV/AC) = $300 + [($1000 – $350) / (0.875 * 1.167)] = $937 As the project will be impacted by the current cost performance and current schedule performance, the formula would be: EAC = AC + [(BAC-EV)/(SPI*CPI)] SPI = EV / PV = $350 / $400 = 0.875 CPI = EV / AC = $350 / $300 = 1.167 EAC = BAC/(EV/AC) = $300 + [($1000 – $350) / (0.875 * 1.167)] = $937 |
|