1.

For The Project With Earned Value (ev) = $350, Actual Cost (ac) = $300 And Planned Value (pv) = $400. The Original Project Budget Is $1,000. Assuming The Remaining Work Will Be Impacted By The Current Cost Performance And Current Schedule Performance, What Is The Estimate At Completion (eac) Of The Project?

Answer»

As the PROJECT will be impacted by the current cost performance and current SCHEDULE performance,

the formula would be:

EAC = AC + [(BAC-EV)/(SPI*CPI)]

SPI = EV / PV = $350 / $400 = 0.875

CPI = EV / AC = $350 / $300 = 1.167

EAC = BAC/(EV/AC) = $300 + [($1000 – $350) / (0.875 * 1.167)] = $937

As the project will be impacted by the current cost performance and current schedule performance,

the formula would be:

EAC = AC + [(BAC-EV)/(SPI*CPI)]

SPI = EV / PV = $350 / $400 = 0.875

CPI = EV / AC = $350 / $300 = 1.167

EAC = BAC/(EV/AC) = $300 + [($1000 – $350) / (0.875 * 1.167)] = $937



Discussion

No Comment Found

Related InterviewSolutions