According To Evm, Which Term Below Represents The Budgeted Cost Of The Work To Be Completed To Date?

Answer»

By definition, PLANNED VALUE (PV) is how MUCH value of work was scheduled to achieve to DATE.

By definition, Planned Value (PV) is how much value of work was scheduled to achieve to date.