1.

If A Project Has A Cost Performance Index (cpi) Of 0.90, This Means That:

Answer»

The Cost Performance INDEX (CPI) represents the performance of the project in terms of budget up to the moment. If it is smaller than 1, the project is CURRENTLY over budget (i.e. has SPENT more than what has been planned).

The Cost Performance Index (CPI) represents the performance of the project in terms of budget up to the moment. If it is smaller than 1, the project is currently over budget (i.e. has spent more than what has been planned).



Discussion

No Comment Found

Related InterviewSolutions