With Reference To The Diagram Below, It Can Be Inferred That The Project Is Currently: |
|
Answer» As of today, AC > PV = over BUDGET and EV < PV = BEHIND schedule, so the project is both “behind schedule and over budget”. As of today, AC > PV = over budget and EV < PV = behind schedule, so the project is both “behind schedule and over budget”. |
|