1.

_______________ tendering is used when all the information necessary to calculate a realistic price is available when tendering commences.(a) Single-stage(b) Double-stage(c) Framework(d) SerialThis question was addressed to me in an interview.I would like to ask this question from Contract System in chapter P.W.D of Civil Engineering Drawing

Answer»

Right choice is (a) Single-stage

Best explanation: Single-stage TENDERING is the more traditional route, used when all the information necessary to calculate a realistic price is available when tendering commences:

• An invitation to tender is issued to prospective suppliers (perhaps following completion of a pre-qualification questionnaire and/or a pre-tender interview). The invitation to tender will include information describing the goods or services required in sufficient detail to enable prospective suppliers to prepare an accurate tender.

• Tenders are PREPARED and returned by prospective suppliers (this may involve questions and answers and a mid-tender interview to clarify the client’s REQUIREMENTS).

• Submitted tenders are then assessed and compared (this may involve further interviews).

• The preferred tenderer is SELECTED and negotiations opened.

• Subject to the OUTCOME of those negotiations the preferred tenderer may then be appointed.