Explore topic-wise InterviewSolutions in .

This section includes InterviewSolutions, each offering curated multiple-choice questions to sharpen your knowledge and support exam preparation. Choose a topic below to get started.

1.

Water use efficiency in the field can be determined as follows:(a) = (Water Transpired by Crop x Water Applied to Field) % 100.(b) False(c) TrueI have been asked this question in a job interview.I'm obligated to ask this question of Earthwork and Estimation in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct ANSWER is (a) = (WATER TRANSPIRED by Crop x Water Applied to Field) % 100.

To explain: Field Water EFFICIENCY (%) = (Water Transpired by Crop %Water Applied to Field) x 100.

2.

________________ is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate.(a) Prime cost(b) Provisional sum(c) Capital cost(d) Building cost indexI had been asked this question in exam.Asked question is from Different Types Of Estimates in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Right OPTION is (b) Provisional sum

Easiest explanation: The work like installation of refrigerating machine; installation of LIFT, AIR conditioning, ETC., for which full information and details may not be KNOWN at the time of preparing estimate and entering into contract and are require to be installed by a specialised firm, a sum.

3.

__________ is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality.(a) Cube Rate Estimate(b) Supplementary Estimate(c) Maintenance Estimate(d) Plinth Area EstimateThe question was posed to me in final exam.I'd like to ask this question from Different Types Of Estimates in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer» RIGHT CHOICE is (d) PLINTH Area Estimate

Easiest explanation: Plinth area estimate is calculated by finding the plinth area of the building and MULTIPLYING by the plinth area rate. The plinth area should be calculated for the covered area by taking external dimension of the building at the FLOOR level.
4.

Approximate cost of a hostel building for 100 students @Rs.10000/- per student works out as Rs. 10 lakhs.(a) True(b) FalseI had been asked this question in a national level competition.This question is from Different Types Of Estimates in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct answer is (a) True

To explain: Approx. cost of a BED hospital @ Rs.50000/- per bed COMES to Rs.50 lakhs.

Approx. cost of a barrack of 10 BAYS @10000/- per BAY comes to Rs.1 lakh.

5.

In __________ irrigation, water is piped to one or more central locations within the field and distributed by overhead high-pressure sprinklers or guns.(a) sprinkler(b) drip(c) shallow(d) rotaryI got this question in unit test.I'd like to ask this question from Earthwork and Estimation topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer» CORRECT option is (a) sprinkler

The explanation is: A system utilizing sprinklers, SPRAYS, or guns mounted overhead on permanently installed risers is often referred to as a solid-set irrigation system. Higher pressure sprinklers that rotate are called rotors and are DRIVEN by a ball drive, gear drive, or impact mechanism. Rotors can be designed to rotate in a FULL or partial circle.
6.

Well development is the process of removing fine sediment and drilling fluid from the area immediately surrounding the perforations.(a) True(b) FalseThe question was asked during a job interview.This is a very interesting question from Wells topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct option is (a) True

Easy EXPLANATION: This increases the well’s ABILITY to produce WATER and maximize production from the aquifer. If the aquifer formation does not naturally have any relatively coarse particles to form a filter, it may be necessary for the driller to install an artificial filter pack. This pack is placed around the screen or PERFORATIONS so the well can be developed. For example, this procedure is necessary when the aquifer is composed of FINE sand and the individual grains are uniform.

7.

A culvert can be used to span over a canyon, or depression, or even over a freeway or roadway.(a) True(b) FalseI have been asked this question by my college director while I was bunking the class.Asked question is from Culverts in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct ANSWER is (b) False

To explain: A BRIDGE doesn’t necessarily have to bridge over WATER. A bridge can be used to SPAN over a canyon, or depression, or even over a freeway or roadway.

8.

The approx. cost of 10 km length of irrigation channel of 3 cu m per sec. capacity @ Rs.70000/- per km works out as Rs.7 lakh.(a) True(b) FalseI got this question in exam.Origin of the question is Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer» RIGHT answer is (a) True

Best EXPLANATION: For an IRRIGATION project having a commanded area 2000 hectares, approx. cost @ Rs.1000/- per hectare comes to Rs.20 lakhs.
9.

Subsurface Textile Irrigation (SSTI) is a technology designed specifically for subirrigation in only desert sands and heavy clays.(a) True(b) FalseI have been asked this question in unit test.My query is from Earthwork and Estimation in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer» CORRECT answer is (b) False

Best explanation: Subsurface Textile Irrigation (SSTI) is a TECHNOLOGY designed specifically for subirrigation in all soil textures from desert sands to heavy clays. A typical subsurface textile irrigation system has an IMPERMEABLE base layer (usually polyethylene or polypropylene), a drip line running along that base, a layer of GEOTEXTILE on top of the drip line and, finally, a NARROW impermeable layer on top of the geotextile.
10.

Subirrigation has been used for many years in field crops in areas with high water tables.(a) True(b) FalseI have been asked this question in a job interview.This interesting question is from Earthwork and Estimation topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Right choice is (a) True

Best explanation: It is a method of artificially raising the water table to allow the soil to be moistened from below the plants’ ROOT zone. Often those SYSTEMS are LOCATED on permanent grasslands in lowlands or river VALLEYS and combined with drainage infrastructure. A system of pumping stations, canals, weirs and GATES allows it to increase or decrease the water level in a network of ditches and thereby control the water table.

11.

_________ culverts have a concrete (sometimes other materials can be used too) floor allowing the water to flow smoothly through it.(a) Box(b) Cylindrical(c) Narrow(d) LongThis question was posed to me in exam.My enquiry is from Culverts topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct option is (a) Box

The best I can explain: Box culverts are usually MADE up of Reinforced Concrete (RCC). Some box culverts can be built using composite structures and are great when water needs to change direction or when a large flow of water is expected. Box culverts can also be installed in such WAY that the top of the culvert is also the ROADWAY surface. The most challenging part of installing these type of culverts is that you generally will need to have a dry surface to install the culvert, so dewatering or DIVERSION of the water will be needed to complete the installation.

12.

___________ is the injection of fertilizers, soil amendments, and other water-soluble products into an irrigation system.(a) Fertilization(b) Hybridization(c) Fertigation(d) ModificationI had been asked this question in semester exam.My enquiry is from Earthwork and Estimation in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct option is (c) Fertigation

Easiest explanation: The two terms are sometimes used INTERCHANGEABLY HOWEVER chemigation is GENERALLY a more controlled and regulated process due to the nature of the chemicals used. Chemigation often INVOLVES pesticides, herbicides, and fungicides, some of which pose health threat to humans, animals, and the ENVIRONMENT.

13.

Shallow or unconfined wells are completed in the uppermost saturated aquifer at that location (the upper unconfined aquifer).(a) True(b) FalseI got this question in homework.I'd like to ask this question from Wells in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The CORRECT choice is (a) True

To elaborate: UNCONFINED aquifers are those into which WATER seeps from the GROUND surface directly above the aquifer.

14.

Name the type of irrigation, which is the oldest form of irrigation and has been in use for thousands of years.(a) Sub-surface irrigation(b) Surface irrigation(c) Canal irrigation(d) Rainwater irrigationThis question was addressed to me in exam.The query is from Earthwork and Estimation topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct choice is (b) Surface irrigation

Explanation: In surface (furrow, flood, or LEVEL basin) irrigation systems, water moves across the surface of an agricultural lands, in an order to wet it and infiltrate into the soil. Surface irrigation can be subdivided into furrow, borderstrip or basin irrigation. It is OFTEN called flood irrigation when the irrigation RESULTS in flooding or near flooding of the cultivated LAND.

15.

Irrigation with saline or high-sodium water may improve the soil structure owing to the formation of fertile soil.(a) False(b) TrueThe question was posed to me in final exam.This question is from Earthwork and Estimation topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Right choice is (a) False

Easiest EXPLANATION: Irrigation with SALINE or high-sodium water may DAMAGE soil structure owing to the FORMATION of alkaline soil.

16.

Drilled wells are smaller in diameter, usually ranging from 10-20 cm (4-8 in.).(a) True(b) FalseI have been asked this question in class test.Origin of the question is Wells topic in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct option is (a) True

Easy explanation: These are completed to much greater depths than bored WELLS, up to several hundred METRES. The producing aquifer is generally less susceptible to POLLUTION from surface sources because of the depth. Also, the water supply tends to be more RELIABLE since it is less affected by seasonal weather patterns.

17.

Drilled wells can be excavated by simple hand drilling methods.(a) True(b) FalseThe question was asked during an interview.The doubt is from Wells in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct OPTION is (a) True

Best explanation: (augering, sludging, jetting, DRIVING, hand PERCUSSION) or machine drilling (rotary, percussion, down the hole hammer). Deeprock rotary drilling method is most common. Rotary can be used in 90% of formation types.

Drilled wells can GET WATER from a much deeper level than dug wells can—often down to several hundred metres.

18.

Production or pumping wells, are often smaller diameter wells used to monitor the hydraulic head or sample the groundwater for chemical constituents.(a) True(b) FalseThe question was asked in examination.I want to ask this question from Wells topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct answer is (a) True

The EXPLANATION: Monitoring wells or piezometers, are often SMALLER diameter wells used to monitor the hydraulic head or SAMPLE the groundwater for chemical constituents. Piezometers are monitoring wells COMPLETED over a very short section of aquifer. Monitoring wells can also be completed at multiple levels, allowing discrete samples or measurements to be made at different vertical ELEVATIONS at the same map location.

19.

Per kilometre basis depending on the nature of road, for 10 km of a state highway approx. cost @ Rs. 50000/- per 1 km works out as Rs. 5 lakh.(a) True(b) FalseThis question was posed to me in an interview.This is a very interesting question from Different Types Of Estimates topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer» CORRECT option is (b) False

To explain: Per KILOMETRE basis depending on the nature of road, for 10 km of a state highway approx. cost @ Rs. 500000/- per 1 km works out as Rs. 50 lakh.
20.

For storeyed building plinth area estimate is not prepared for each storey separately.(a) True(b) FalseThis question was posed to me in unit test.My question is based upon Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer» CORRECT answer is (B) False

To elaborate: For storeyed building PLINTH area estimate is prepared for each storey SEPARATELY.
21.

___________ is the application of controlled amounts of water to plants at needed intervals.(a) Cultivation(b) Plantation(c) Watering(d) IrrigationThis question was posed to me during an interview.This is a very interesting question from Earthwork and Estimation in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Right choice is (d) Irrigation

The best explanation: Irrigation helps grow agricultural CROPS, maintain landscapes, and revegetate disturbed soils in dry areas and during periods of inadequate RAINFALL. Irrigation also has other uses in CROP production, including frost protection, SUPPRESSING weed growth in grain fields and preventing soil. In contrast, agriculture that relies only on direct rainfall is referred to as rain-fed or dry land farming.

22.

The process of removing culverts, which is becoming increasingly prevalent, is known as ___________(a) outlighting(b) culverting(c) daylighting(d) inlightingI have been asked this question during a job interview.My enquiry is from Culverts topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Right choice is (c) daylighting

Explanation: In URBAN design and urban planning, daylighting is the redirection of a stream into an above-ground channel. Typically, the goal is to restore a stream of water to a more NATURAL state. Daylighting is intended to improve the riparian environment for a stream which had been previously DIVERTED into a culvert, PIPE, or a drainage SYSTEM.

23.

Around 30% of wastewater produced globally remains untreated, causing widespread water pollution.(a) True(b) FalseI got this question in homework.This intriguing question originated from Earthwork and Estimation in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct choice is (B) False

Easiest explanation: Around 90% of wastewater produced GLOBALLY remains untreated, causing widespread water pollution. Increasingly, agriculture uses untreated wastewater as a source of IRRIGATION water. Cities provide lucrative markets for fresh PRODUCE, so are attractive to farmers.

24.

An _________ is an underground layer of water-bearing permeable rock, rock fractures or unconsolidated materials (gravel, sand, or silt) from which groundwater can be extracted using a water well.(a) Aquitard(b) Aqifuge(c) Aquiclude(d) AquiferThe question was asked in an interview for job.The question is from Wells topic in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct option is (d) AQUIFER

The explanation is: An aquifer is an underground layer of water-bearing permeable rock, rock fractures or unconsolidated materials (GRAVEL, sand, or silt) from which groundwater can be EXTRACTED using a water well. The study of water flow in aquifers and the CHARACTERIZATION of aquifers is called hydrogeology.

25.

Box culverts can be defined as a passage for water over a natural ground having a deck slab over it as path way for vehicles.(a) True(b) FalseThis question was addressed to me in final exam.This interesting question is from Culverts in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct choice is (b) False

The explanation: Slab culvert- A passage for water over a natural GROUND having a deck slab over it as path WAY for vehicles.

Box culvert – Box culverts are usually MADE up of Reinforced Concrete (RCC) as a box SHAPED tunnel through which the water flows and the VEHICULAR transmission takes place over the box.

26.

A structure that allows water to flow under a road, railroad, trail, or similar obstruction from one side to the other side is called as ______________(a) drainage(b) bridges(c) tunnel(d) culvertsThis question was posed to me by my college director while I was bunking the class.Query is from Culverts in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct answer is (d) CULVERTS

To elaborate: Culverts are commonly used both as cross-drains for ditch relief and to pass WATER under a road at NATURAL drainage and stream crossings. A culvert may be a bridge-like structure designed to allow VEHICLE or pedestrian traffic to cross over the waterway while allowing adequate passage for the water.

27.

What does IWMI stand for?(a) International Water Management Institute(b) International Weather Management Institute(c) Irrigation Water Management Institute(d) International Waste Management InstituteThe question was asked in an interview for job.Asked question is from Earthwork and Estimation topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct option is (a) INTERNATIONAL Water Management Institute

The best I can explain: The International Water Management Institute IWMI is a non-profit RESEARCH organisation with headquarters in Colombo, Sri Lanka, and OFFICES across Africa and Asia. Research at the Institute focuses on improving how water and land RESOURCES are managed, with the aim of UNDERPINNING food security and reducing poverty while safeguarding vital environmental processes.

28.

__________ wells are constructed when low yielding groundwater sources are found relatively close to the surface, usually under 30 m (100 ft.). These are constructed using a rotary bucket auger.(a) Cap(b) Drilling(c) Bored(d) SurfaceThis question was addressed to me during an interview.My question is based upon Wells topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct option is (c) Bored

Easiest explanation: They are USUALLY completed by PERFORATING the casing (also called cribbing) or using a sand screen with continuous slot openings (Bored Well). One ADVANTAGE of bored wells is the large diameter of the casing, from 45-90 cm (18-36 in.). It provides a water storage reservoir for use during peak demand periods. A disadvantage of utilizing a shallow groundwater aquifer is that it GENERALLY relies on annual precipitation for recharge. Water shortages may OCCUR following long dry periods in summer and extended freeze up during winter months. It can also be more susceptible to contamination from surface land-use activities.

29.

Culverts cannot be constructed of a variety of materials including cast-in-place or precast concrete.(a) True(b) FalseThe question was posed to me in my homework.The origin of the question is Culverts topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct answer is (b) False

To explain I would say: CULVERTS can be constructed of a variety of materials including cast-in-place or precast concrete (reinforced or non-reinforced), galvanized STEEL, aluminium, or plastic, typically high-density polyethylene. TWO or more materials may be combined to form composite structures. For example, open-bottom corrugated steel structures are OFTEN built on concrete FOOTINGS.

30.

A large work or project may consists of several building or small works and each of these work is known as ___________(a) sub-work(b) sub-project(c) sub-head(d) sub-constructionThe question was posed to me in final exam.Question is taken from Different Types Of Estimates in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct CHOICE is (a) sub-work

The explanation: DETAILED ESTIMATE of each sub-work is prepared separately and ACCOUNTS of expenditure are KEPT sub-work wise.

31.

Name the system, where water falls drop by drop just at the position of roots and water is delivered at or near the root zone of plants, drop by drop.(a) Pipe irrigation(b) Drop irrigation(c) Drip irrigation(d) SprinklerI got this question during an interview for a job.Asked question is from Earthwork and Estimation in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct choice is (c) DRIP irrigation

For explanation I would SAY: This method can be the most water-efficient method of irrigation, if managed PROPERLY, evaporation and runoff are minimized. The FIELD water efficiency of drip irrigation is typically in the range of 80 to 90 percent when managed correctly.

32.

In this method approx. total length of walls is found in running metre and this total length multiplied by the rate per running metre of wall gives a fairly accurate cost.(a) Annual repair(b) Item rate estimate(c) Approximate quantity method estimate(d) Cubical content estimateThis question was posed to me in an online interview.My doubt is from Different Types Of Estimates topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct option is (c) APPROXIMATE quantity METHOD estimate

The best I can explain: For this method the structure may be DIVIDED into two PARTS VIZ. Foundation including plinth and Superstructure.

33.

Cube rate estimate is less accurate as compared to the plinth area estimate as the height of the building is also compared.(a) False(b) TrueI had been asked this question by my college director while I was bunking the class.Query is from Different Types Of Estimates topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct OPTION is (b) True

To elaborate: Cube RATE ESTIMATE is most accurate as compared to the plinth area estimate as the height of the BUILDING is ALSO compared.

34.

In the following figure, Part 2 represents?(a) cut-out(b) generator(c) jet pump with pressure switch(d) power sourceThis question was addressed to me in an online interview.My query is from Wells topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct choice is (c) jet PUMP with PRESSURE switch

The EXPLANATION is: A pump-jet, hydrojet, or water jet is a marine system that creates a jet of water for propulsion. The mechanical arrangement may be a ducted propeller (AXIAL-flow pump), a centrifugal pump, or a mixed flow pump which is a combination of both centrifugal and axial DESIGNS. The design also incorporates an intake to provide water to the pump and a nozzle to direct the flow of water out of the pump.

35.

Sealing the well protects the well’s producing zone from contamination.(a) True(b) FalseI had been asked this question during an interview for a job.This is a very interesting question from Wells in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct choice is (a) True

The explanation is: The diameter of the borehole is usually slightly LARGER than the casing being installed. The space between the borehole and the casing is called the annulus of the well or the ANNULAR space. It must be sealed to PREVENT any surface CONTAMINATION from migrating downward and contaminating the WATER supply. A properly sealed annulus also prevents any mixing of poor quality water from upper aquifers with water from the producing aquifer of the well.

36.

An _________ culvert is normally a low profile culvert. It allows them to be installed without disturbing the causeway as it will span over the entire drainage width.(a) box(b) rectangle(c) arch(d) circularThe question was asked in class test.The query is from Culverts topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct choice is (c) arch

For explanation: They are normally made of METAL, stone masonry or RCC. They are installed easily, and you don’t need to use expensive water diversion structures to install it. Common shapes INCLUDE SEMICIRCULAR arch, elliptical arch, and concrete box culverts.Another benefit of these type of structure is that the installation process will not take a lot of TIME, COMPARED to traditional box culverts.

37.

Construction or installation at a culvert site generally results in disturbance of the site soil.(a) True(b) FalseI had been asked this question during an interview for a job.I'd like to ask this question from Culverts topic in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer» CORRECT choice is (a) True

Best explanation: Construction or installation at a culvert site generally results in disturbance of the site soil, stream BANKS, or streambed, and can result in the OCCURRENCE of unwanted PROBLEMS such as scour holes or slumping of banks ADJACENT to the culvert structure.
38.

If the span of crossing is greater than 12 feet (3.7 m), the structure is termed as bridge and otherwise is culvert.(a) True(b) FalseI had been asked this question during an internship interview.I'd like to ask this question from Culverts in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct ANSWER is (a) True

The explanation: A bridge is a structure built to span physical obstacles WITHOUT closing the way underneath such as a body of water, VALLEY, or ROAD, for the purpose of providing passage over the OBSTACLE. There are many different designs that each serve a particular purpose and apply to different situations.

39.

A commercially manufactured, vermin-proof _________ is the only type of cap designed to keep animals, insects and contaminants from entering your well.(a) animal cap(b) security cap(c) danger cap(d) well capI had been asked this question in an interview for job.My enquiry is from Wells in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct choice is (d) well cap

The best I can explain: It comes equipped with rubber gaskets and screened vents to ENSURE vermin stay out and air can circulate through. Coverings for large diameter wells must be CUSTOM MADE because of their LARGER size. Ideally they should be made of steel, or FIBREGLASS or plastic that is stamped for potable water use.

40.

Water wells typically range from 3 to 18 metres (10–60 ft) deep, but in some areas can go deeper than 200 metre.(a) True(b) FalseThis question was posed to me during an internship interview.This interesting question is from Wells topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer» CORRECT answer is (b) False

The explanation is: WATER wells typically range from 3 to 18 metres (10–60 ft) deep, but in some areas can go DEEPER than 900 metres (3,000 ft).
41.

To make out an estimate for a work the following data are necessary-Drawing, Specification and ___________(a) materials(b) rates(c) labours(d) transportationI got this question by my college director while I was bunking the class.My question comes from Different Types Of Estimates topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct OPTION is (b) RATES

Explanation: The rates per UNIT of various items of work, the rates of various materials to be used in the construction, and the wages of DIFFERENT category of labour, skilled or unskilled as mason, carpenter, mazdoor, BHISHTI etc. available for preparing estimate.

42.

The term ______________ is used to denote a procedure of costing or valuing an item of work on the basis of actual labourers and materials required.(a) prime cost(b) hour-work(c) day-work(d) sub-workThis question was addressed to me during an interview for a job.The origin of the question is Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct option is (c) day-work

For explanation: Certain items of work which cannot be measured as- a design in the PLASTER work, front ARCHITECTURAL finish of a building, work under water, etc. are valued and paid by ‘day work’. In such CASES the schedule of rates of materials and different CLASSES of LABOURERS likely to be engaged in th work should be included in the tender and in contract agreement.

43.

A structure that carries water above land is known as an _____________(a) aqueduct(b) aquedant(c) over surface(d) outlandI had been asked this question in quiz.The query is from Culverts topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct answer is (a) aqueduct

For explanation: Bridges for conveying water, CALLED aqueducts or water bridges are constructed to convey watercourses across gaps such as valleys or ravines. The term aqueduct MAY also be used to refer to the entire watercourse, as well as the bridge. LARGE navigable aqueducts are used as transport links for boats or ships.

44.

_______________ estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.(a) Supplementary and revised estimate(b) Maintenance estimate(c) Item rate estimate(d) Revised estimateThe question was posed to me during an internship interview.My question is based upon Different Types Of Estimates in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Correct answer is (b) Maintenance estimate

The EXPLANATION is: For building; this INCLUDES white washing, colour washing, painting, minor repairs etc. For road works the A.R. estimate provides for PATCH repairing, renewals, REPAIR of culverts, etc.

45.

____________ sometimes also called as localized irrigation, low volume irrigation, or trickle irrigation.(a) Macro-irrigation(b) Surface irrigation(c) Micro-irrigation(d) Farrow irrigationThe question was asked during an interview.This is a very interesting question from Earthwork and Estimation in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct choice is (C) Micro-irrigation

The best explanation: It is a system where water is distributed under low pressure through a PIPED network, in a pre-determined pattern, and applied as a SMALL discharge to each plant or adjacent to it. Traditional drip irrigation using individual emitters, subsurface drip irrigation (SDI), micro-spray or micro-sprinkler irrigation, and mini-bubbler irrigation all belong to this CATEGORY of irrigation METHODS.

46.

In the following figure, Part 1 represents?(a) inlet pipe(b) well(c) drainage pipe(d) outlet pipeThe question was asked during an online interview.I need to ask this question from Wells topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer» RIGHT answer is (b) well

For explanation: A WATER well is an excavation or STRUCTURE created in the ground by digging, driving, boring, or drilling to access groundwater in UNDERGROUND aquifers. The well water is drawn by a pump, or using CONTAINERS, such as buckets, that are raised mechanically or by hand.
47.

Approx. cost of a bridge of 3 spans of 50 m each span @Rs.30000/- per running m of span comes to 3*50*30000 = Rs. 45 lakhs.(a) True(b) FalseI had been asked this question in unit test.My enquiry is from Different Types Of Estimates topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Right choice is (a) True

Easy EXPLANATION: Per running metre of span depending on the roadway, NATURE and depth of foundation, type of structure, etc. For small CULVERTS approx. cost may also be per NUMBER of culverts of different SPANS.

48.

_________________ is required for preliminary studies of various aspects of a work or project.(a) Supplementary Estimate(b) Plinth Area Estimate(c) Revised Estimate(d) Abstract EstimateI have been asked this question in class test.The doubt is from Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Right choice is (d) Abstract Estimate

The explanation is: to decide the financial position and policy for administrative SANCTION by thecompetent administrative authority. In CASE of commercial projects as irrigation projects as irrigation projects, RESIDENTIAL BUILDING projects and similar projects which earn revenue income, the probable income may be WORKED out.

49.

There are two primary methods of drilling cable tool and ________(a) Rotary(b) Rotatory(c) Penetrating(d) InsertionThis question was posed to me at a job interview.My question comes from Wells topic in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct choice is (a) Rotary

The explanation: Rotary drilled wells are constructed using a DRILL bit on the end of a rotating drillstem. Drilling fluid or air is circulated down through the drillstem in the hole and back to the surface to remove cuttings. Rotary drilling RIGS operate quickly and can reach depths of over 300 m (1000 ft.), with CASING diameters of 10-45 cm (4-18 in.).

Cable tool drilled wells are constructed by LIFTING and dropping a heavy drill bit in the bore hole. The resulting loose material, mixed with water, is removed using a bailer or sand pump. This method, also called percussion drilling, reaches depths up to 300 m (1000 ft.). Well diameters can range from 10-45 cm (4-18 in.). The drilling rate is typically much slower than for a rotary rig, but when aquifers are low yielding, they may be more easily identified using this method.

50.

If the impermeable area overlies the aquifer, pressure could cause it to become a confined aquifer.(a) True(b) FalseThe question was asked in an international level competition.This interesting question is from Wells in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer» CORRECT ANSWER is (a) True

Best EXPLANATION: Confined aquifers are those in which an impermeable dirt/rock layer exists that prevents water from seeping into the aquifer from the ground surface located directly above.