InterviewSolution
This section includes InterviewSolutions, each offering curated multiple-choice questions to sharpen your knowledge and support exam preparation. Choose a topic below to get started.
| 1. |
Water use efficiency in the field can be determined as follows:(a) = (Water Transpired by Crop x Water Applied to Field) % 100.(b) False(c) TrueI have been asked this question in a job interview.I'm obligated to ask this question of Earthwork and Estimation in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct ANSWER is (a) = (WATER TRANSPIRED by Crop x Water Applied to Field) % 100. |
|
| 2. |
________________ is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate.(a) Prime cost(b) Provisional sum(c) Capital cost(d) Building cost indexI had been asked this question in exam.Asked question is from Different Types Of Estimates in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Right OPTION is (b) Provisional sum |
|
| 3. |
__________ is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality.(a) Cube Rate Estimate(b) Supplementary Estimate(c) Maintenance Estimate(d) Plinth Area EstimateThe question was posed to me in final exam.I'd like to ask this question from Different Types Of Estimates in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» RIGHT CHOICE is (d) PLINTH Area Estimate Easiest explanation: Plinth area estimate is calculated by finding the plinth area of the building and MULTIPLYING by the plinth area rate. The plinth area should be calculated for the covered area by taking external dimension of the building at the FLOOR level. |
|
| 4. |
Approximate cost of a hostel building for 100 students @Rs.10000/- per student works out as Rs. 10 lakhs.(a) True(b) FalseI had been asked this question in a national level competition.This question is from Different Types Of Estimates in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct answer is (a) True |
|
| 5. |
In __________ irrigation, water is piped to one or more central locations within the field and distributed by overhead high-pressure sprinklers or guns.(a) sprinkler(b) drip(c) shallow(d) rotaryI got this question in unit test.I'd like to ask this question from Earthwork and Estimation topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» CORRECT option is (a) sprinkler The explanation is: A system utilizing sprinklers, SPRAYS, or guns mounted overhead on permanently installed risers is often referred to as a solid-set irrigation system. Higher pressure sprinklers that rotate are called rotors and are DRIVEN by a ball drive, gear drive, or impact mechanism. Rotors can be designed to rotate in a FULL or partial circle. |
|
| 6. |
Well development is the process of removing fine sediment and drilling fluid from the area immediately surrounding the perforations.(a) True(b) FalseThe question was asked during a job interview.This is a very interesting question from Wells topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct option is (a) True |
|
| 7. |
A culvert can be used to span over a canyon, or depression, or even over a freeway or roadway.(a) True(b) FalseI have been asked this question by my college director while I was bunking the class.Asked question is from Culverts in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct ANSWER is (b) False |
|
| 8. |
The approx. cost of 10 km length of irrigation channel of 3 cu m per sec. capacity @ Rs.70000/- per km works out as Rs.7 lakh.(a) True(b) FalseI got this question in exam.Origin of the question is Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» RIGHT answer is (a) True Best EXPLANATION: For an IRRIGATION project having a commanded area 2000 hectares, approx. cost @ Rs.1000/- per hectare comes to Rs.20 lakhs. |
|
| 9. |
Subsurface Textile Irrigation (SSTI) is a technology designed specifically for subirrigation in only desert sands and heavy clays.(a) True(b) FalseI have been asked this question in unit test.My query is from Earthwork and Estimation in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» CORRECT answer is (b) False Best explanation: Subsurface Textile Irrigation (SSTI) is a TECHNOLOGY designed specifically for subirrigation in all soil textures from desert sands to heavy clays. A typical subsurface textile irrigation system has an IMPERMEABLE base layer (usually polyethylene or polypropylene), a drip line running along that base, a layer of GEOTEXTILE on top of the drip line and, finally, a NARROW impermeable layer on top of the geotextile. |
|
| 10. |
Subirrigation has been used for many years in field crops in areas with high water tables.(a) True(b) FalseI have been asked this question in a job interview.This interesting question is from Earthwork and Estimation topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Right choice is (a) True |
|
| 11. |
_________ culverts have a concrete (sometimes other materials can be used too) floor allowing the water to flow smoothly through it.(a) Box(b) Cylindrical(c) Narrow(d) LongThis question was posed to me in exam.My enquiry is from Culverts topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct option is (a) Box |
|
| 12. |
___________ is the injection of fertilizers, soil amendments, and other water-soluble products into an irrigation system.(a) Fertilization(b) Hybridization(c) Fertigation(d) ModificationI had been asked this question in semester exam.My enquiry is from Earthwork and Estimation in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct option is (c) Fertigation |
|
| 13. |
Shallow or unconfined wells are completed in the uppermost saturated aquifer at that location (the upper unconfined aquifer).(a) True(b) FalseI got this question in homework.I'd like to ask this question from Wells in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The CORRECT choice is (a) True |
|
| 14. |
Name the type of irrigation, which is the oldest form of irrigation and has been in use for thousands of years.(a) Sub-surface irrigation(b) Surface irrigation(c) Canal irrigation(d) Rainwater irrigationThis question was addressed to me in exam.The query is from Earthwork and Estimation topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct choice is (b) Surface irrigation |
|
| 15. |
Irrigation with saline or high-sodium water may improve the soil structure owing to the formation of fertile soil.(a) False(b) TrueThe question was posed to me in final exam.This question is from Earthwork and Estimation topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Right choice is (a) False |
|
| 16. |
Drilled wells are smaller in diameter, usually ranging from 10-20 cm (4-8 in.).(a) True(b) FalseI have been asked this question in class test.Origin of the question is Wells topic in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct option is (a) True |
|
| 17. |
Drilled wells can be excavated by simple hand drilling methods.(a) True(b) FalseThe question was asked during an interview.The doubt is from Wells in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct OPTION is (a) True |
|
| 18. |
Production or pumping wells, are often smaller diameter wells used to monitor the hydraulic head or sample the groundwater for chemical constituents.(a) True(b) FalseThe question was asked in examination.I want to ask this question from Wells topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct answer is (a) True |
|
| 19. |
Per kilometre basis depending on the nature of road, for 10 km of a state highway approx. cost @ Rs. 50000/- per 1 km works out as Rs. 5 lakh.(a) True(b) FalseThis question was posed to me in an interview.This is a very interesting question from Different Types Of Estimates topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» CORRECT option is (b) False To explain: Per KILOMETRE basis depending on the nature of road, for 10 km of a state highway approx. cost @ Rs. 500000/- per 1 km works out as Rs. 50 lakh. |
|
| 20. |
For storeyed building plinth area estimate is not prepared for each storey separately.(a) True(b) FalseThis question was posed to me in unit test.My question is based upon Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» CORRECT answer is (B) False To elaborate: For storeyed building PLINTH area estimate is prepared for each storey SEPARATELY. |
|
| 21. |
___________ is the application of controlled amounts of water to plants at needed intervals.(a) Cultivation(b) Plantation(c) Watering(d) IrrigationThis question was posed to me during an interview.This is a very interesting question from Earthwork and Estimation in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Right choice is (d) Irrigation |
|
| 22. |
The process of removing culverts, which is becoming increasingly prevalent, is known as ___________(a) outlighting(b) culverting(c) daylighting(d) inlightingI have been asked this question during a job interview.My enquiry is from Culverts topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Right choice is (c) daylighting |
|
| 23. |
Around 30% of wastewater produced globally remains untreated, causing widespread water pollution.(a) True(b) FalseI got this question in homework.This intriguing question originated from Earthwork and Estimation in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct choice is (B) False |
|
| 24. |
An _________ is an underground layer of water-bearing permeable rock, rock fractures or unconsolidated materials (gravel, sand, or silt) from which groundwater can be extracted using a water well.(a) Aquitard(b) Aqifuge(c) Aquiclude(d) AquiferThe question was asked in an interview for job.The question is from Wells topic in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct option is (d) AQUIFER |
|
| 25. |
Box culverts can be defined as a passage for water over a natural ground having a deck slab over it as path way for vehicles.(a) True(b) FalseThis question was addressed to me in final exam.This interesting question is from Culverts in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct choice is (b) False |
|
| 26. |
A structure that allows water to flow under a road, railroad, trail, or similar obstruction from one side to the other side is called as ______________(a) drainage(b) bridges(c) tunnel(d) culvertsThis question was posed to me by my college director while I was bunking the class.Query is from Culverts in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct answer is (d) CULVERTS |
|
| 27. |
What does IWMI stand for?(a) International Water Management Institute(b) International Weather Management Institute(c) Irrigation Water Management Institute(d) International Waste Management InstituteThe question was asked in an interview for job.Asked question is from Earthwork and Estimation topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct option is (a) INTERNATIONAL Water Management Institute |
|
| 28. |
__________ wells are constructed when low yielding groundwater sources are found relatively close to the surface, usually under 30 m (100 ft.). These are constructed using a rotary bucket auger.(a) Cap(b) Drilling(c) Bored(d) SurfaceThis question was addressed to me during an interview.My question is based upon Wells topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct option is (c) Bored |
|
| 29. |
Culverts cannot be constructed of a variety of materials including cast-in-place or precast concrete.(a) True(b) FalseThe question was posed to me in my homework.The origin of the question is Culverts topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct answer is (b) False |
|
| 30. |
A large work or project may consists of several building or small works and each of these work is known as ___________(a) sub-work(b) sub-project(c) sub-head(d) sub-constructionThe question was posed to me in final exam.Question is taken from Different Types Of Estimates in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct CHOICE is (a) sub-work |
|
| 31. |
Name the system, where water falls drop by drop just at the position of roots and water is delivered at or near the root zone of plants, drop by drop.(a) Pipe irrigation(b) Drop irrigation(c) Drip irrigation(d) SprinklerI got this question during an interview for a job.Asked question is from Earthwork and Estimation in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct choice is (c) DRIP irrigation |
|
| 32. |
In this method approx. total length of walls is found in running metre and this total length multiplied by the rate per running metre of wall gives a fairly accurate cost.(a) Annual repair(b) Item rate estimate(c) Approximate quantity method estimate(d) Cubical content estimateThis question was posed to me in an online interview.My doubt is from Different Types Of Estimates topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct option is (c) APPROXIMATE quantity METHOD estimate |
|
| 33. |
Cube rate estimate is less accurate as compared to the plinth area estimate as the height of the building is also compared.(a) False(b) TrueI had been asked this question by my college director while I was bunking the class.Query is from Different Types Of Estimates topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct OPTION is (b) True |
|
| 34. |
In the following figure, Part 2 represents?(a) cut-out(b) generator(c) jet pump with pressure switch(d) power sourceThis question was addressed to me in an online interview.My query is from Wells topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct choice is (c) jet PUMP with PRESSURE switch |
|
| 35. |
Sealing the well protects the well’s producing zone from contamination.(a) True(b) FalseI had been asked this question during an interview for a job.This is a very interesting question from Wells in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct choice is (a) True |
|
| 36. |
An _________ culvert is normally a low profile culvert. It allows them to be installed without disturbing the causeway as it will span over the entire drainage width.(a) box(b) rectangle(c) arch(d) circularThe question was asked in class test.The query is from Culverts topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct choice is (c) arch |
|
| 37. |
Construction or installation at a culvert site generally results in disturbance of the site soil.(a) True(b) FalseI had been asked this question during an interview for a job.I'd like to ask this question from Culverts topic in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» CORRECT choice is (a) True Best explanation: Construction or installation at a culvert site generally results in disturbance of the site soil, stream BANKS, or streambed, and can result in the OCCURRENCE of unwanted PROBLEMS such as scour holes or slumping of banks ADJACENT to the culvert structure. |
|
| 38. |
If the span of crossing is greater than 12 feet (3.7 m), the structure is termed as bridge and otherwise is culvert.(a) True(b) FalseI had been asked this question during an internship interview.I'd like to ask this question from Culverts in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct ANSWER is (a) True |
|
| 39. |
A commercially manufactured, vermin-proof _________ is the only type of cap designed to keep animals, insects and contaminants from entering your well.(a) animal cap(b) security cap(c) danger cap(d) well capI had been asked this question in an interview for job.My enquiry is from Wells in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct choice is (d) well cap |
|
| 40. |
Water wells typically range from 3 to 18 metres (10–60 ft) deep, but in some areas can go deeper than 200 metre.(a) True(b) FalseThis question was posed to me during an internship interview.This interesting question is from Wells topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» CORRECT answer is (b) False The explanation is: WATER wells typically range from 3 to 18 metres (10–60 ft) deep, but in some areas can go DEEPER than 900 metres (3,000 ft). |
|
| 41. |
To make out an estimate for a work the following data are necessary-Drawing, Specification and ___________(a) materials(b) rates(c) labours(d) transportationI got this question by my college director while I was bunking the class.My question comes from Different Types Of Estimates topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct OPTION is (b) RATES |
|
| 42. |
The term ______________ is used to denote a procedure of costing or valuing an item of work on the basis of actual labourers and materials required.(a) prime cost(b) hour-work(c) day-work(d) sub-workThis question was addressed to me during an interview for a job.The origin of the question is Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct option is (c) day-work |
|
| 43. |
A structure that carries water above land is known as an _____________(a) aqueduct(b) aquedant(c) over surface(d) outlandI had been asked this question in quiz.The query is from Culverts topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct answer is (a) aqueduct |
|
| 44. |
_______________ estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.(a) Supplementary and revised estimate(b) Maintenance estimate(c) Item rate estimate(d) Revised estimateThe question was posed to me during an internship interview.My question is based upon Different Types Of Estimates in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct answer is (b) Maintenance estimate |
|
| 45. |
____________ sometimes also called as localized irrigation, low volume irrigation, or trickle irrigation.(a) Macro-irrigation(b) Surface irrigation(c) Micro-irrigation(d) Farrow irrigationThe question was asked during an interview.This is a very interesting question from Earthwork and Estimation in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct choice is (C) Micro-irrigation |
|
| 46. |
In the following figure, Part 1 represents?(a) inlet pipe(b) well(c) drainage pipe(d) outlet pipeThe question was asked during an online interview.I need to ask this question from Wells topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» RIGHT answer is (b) well For explanation: A WATER well is an excavation or STRUCTURE created in the ground by digging, driving, boring, or drilling to access groundwater in UNDERGROUND aquifers. The well water is drawn by a pump, or using CONTAINERS, such as buckets, that are raised mechanically or by hand. |
|
| 47. |
Approx. cost of a bridge of 3 spans of 50 m each span @Rs.30000/- per running m of span comes to 3*50*30000 = Rs. 45 lakhs.(a) True(b) FalseI had been asked this question in unit test.My enquiry is from Different Types Of Estimates topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Right choice is (a) True |
|
| 48. |
_________________ is required for preliminary studies of various aspects of a work or project.(a) Supplementary Estimate(b) Plinth Area Estimate(c) Revised Estimate(d) Abstract EstimateI have been asked this question in class test.The doubt is from Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Right choice is (d) Abstract Estimate |
|
| 49. |
There are two primary methods of drilling cable tool and ________(a) Rotary(b) Rotatory(c) Penetrating(d) InsertionThis question was posed to me at a job interview.My question comes from Wells topic in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct choice is (a) Rotary |
|
| 50. |
If the impermeable area overlies the aquifer, pressure could cause it to become a confined aquifer.(a) True(b) FalseThe question was asked in an international level competition.This interesting question is from Wells in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» CORRECT ANSWER is (a) True Best EXPLANATION: Confined aquifers are those in which an impermeable dirt/rock layer exists that prevents water from seeping into the aquifer from the ground surface located directly above. |
|