_________________ is required for preliminary studies of various aspects of a work or project.(a) Supplementary Estimate(b) Plinth Area Estimate(c) Revised Estimate(d) Abstract EstimateI have been asked this question in class test.The doubt is from Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

Right choice is (d) Abstract Estimate

The explanation is: to decide the financial position and policy for administrative SANCTION by thecompetent administrative authority. In CASE of commercial projects as irrigation projects as irrigation projects, RESIDENTIAL BUILDING projects and similar projects which earn revenue income, the probable income may be WORKED out.