_________________ is required for preliminary studies of various aspects of a work or project.(a) Supplementary Estimate(b) Plinth Area Estimate(c) Revised Estimate(d) Abstract EstimateI have been asked this question in class test.The doubt is from Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Right choice is (d) Abstract Estimate |
|