InterviewSolution
Saved Bookmarks
| 1. |
In this method approx. total length of walls is found in running metre and this total length multiplied by the rate per running metre of wall gives a fairly accurate cost.(a) Annual repair(b) Item rate estimate(c) Approximate quantity method estimate(d) Cubical content estimateThis question was posed to me in an online interview.My doubt is from Different Types Of Estimates topic in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct option is (c) APPROXIMATE quantity METHOD estimate |
|