_______________ estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.(a) Supplementary and revised estimate(b) Maintenance estimate(c) Item rate estimate(d) Revised estimateThe question was posed to me during an internship interview.My question is based upon Different Types Of Estimates in portion Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» Correct answer is (b) Maintenance estimate |
|