The term ______________ is used to denote a procedure of costing or valuing an item of work on the basis of actual labourers and materials required.(a) prime cost(b) hour-work(c) day-work(d) sub-workThis question was addressed to me during an interview for a job.The origin of the question is Different Types Of Estimates in section Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing |
|
Answer» The correct option is (c) day-work |
|