1.

To make out an estimate for a work the following data are necessary-Drawing, Specification and ___________(a) materials(b) rates(c) labours(d) transportationI got this question by my college director while I was bunking the class.My question comes from Different Types Of Estimates topic in division Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct OPTION is (b) RATES

Explanation: The rates per UNIT of various items of work, the rates of various materials to be used in the construction, and the wages of DIFFERENT category of labour, skilled or unskilled as mason, carpenter, mazdoor, BHISHTI etc. available for preparing estimate.