1.

Cube rate estimate is less accurate as compared to the plinth area estimate as the height of the building is also compared.(a) False(b) TrueI had been asked this question by my college director while I was bunking the class.Query is from Different Types Of Estimates topic in chapter Irrigation Works, Culverts, Bridges and Wells of Civil Engineering Drawing

Answer»

The correct OPTION is (b) True

To elaborate: Cube RATE ESTIMATE is most accurate as compared to the plinth area estimate as the height of the BUILDING is ALSO compared.