| 1. |
Calculate the quantity of earthwork for 200 m length for a portion of road in an uniform ground the heights of banks at the two ends being 1.00 m and 1.60 m. The formation width is 10 mm and side slope 2:1. Assume that there is no traverse slope.(a) 3276 cu m(b) 5676 cu m(c) 6757 cu m(d) 1121 cu mI got this question by my college director while I was bunking the class.This key question is from Estimate of Earthwork by Three Methods topic in division Road Estimating, Sanitary and Water Supply Work of Civil Engineering Drawing |
|
Answer» The CORRECT choice is (a) 3276 CU m |
|