Centring and shuttering for flat surfaces- 4 beldars and 4 carpenters (2 class) can do 9.6 sq m (96 sq ft) per day.(a) True(b) FalseThe question was asked by my college director while I was bunking the class.This intriguing question originated from Estimation of Basic Rates Occurred topic in chapter Analysis of Rates of Civil Engineering Drawing

Answer» CORRECT choice is (a) True

To explain: Reinforcement WORK for R.C.C.- 1 blacksmith or fitter and 1 beldar can bend and place in POSITION 1 quintal (2 cwt) of steel per day.