Centring and shuttering for flat surfaces- 4 beldars and 4 carpenters (2 class) can do 9.6 sq m (96 sq ft) per day.(a) True(b) FalseThe question was asked by my college director while I was bunking the class.This intriguing question originated from Estimation of Basic Rates Occurred topic in chapter Analysis of Rates of Civil Engineering Drawing |
|
Answer» CORRECT choice is (a) True To explain: Reinforcement WORK for R.C.C.- 1 blacksmith or fitter and 1 beldar can bend and place in POSITION 1 quintal (2 cwt) of steel per day. |
|