1.

First coat of bituminous painting shall be with stone ballast no.3 and stone grit of 20 mm gauge at 220 kg of asphalt and 1.35 cu m of stone grit per 100 sq. m.(a) True(b) FalseThe question was posed to me in an interview for job.The origin of the question is General Specifications of Modern Road in portion Specifications, Estimation of Quantities of Materials and Transport of Civil Engineering Drawing

Answer»

The correct choice is (B) False

For explanation I would SAY: FIRST coat of bituminous painting shall be with ASPHALT or Road tar No.3 and stone grit of 20 mm gauge at 220 kg of asphalt and 1.35 cu m of stone grit per 100 sq. m.