1.

For first class building the foundation and plinth shall be of 1st class brickwork in lime mortar or 1:2 cement mortar over lime concrete or 1:6:7 cement concrete.(a) True(b) FalseThe question was asked in my homework.This key question is from General Specifications in division Specifications, Estimation of Quantities of Materials and Transport of Civil Engineering Drawing

Answer»

The correct option is (b) False

Easiest EXPLANATION: Foundation and plinth shall be of 1st class brickwork in LIME MORTAR or 1:6 cement mortar over lime concrete or 1:4:8 cement concrete.