| 1. |
For first class building the foundation and plinth shall be of 1st class brickwork in lime mortar or 1:2 cement mortar over lime concrete or 1:6:7 cement concrete.(a) True(b) FalseThe question was asked in my homework.This key question is from General Specifications in division Specifications, Estimation of Quantities of Materials and Transport of Civil Engineering Drawing |
|
Answer» The correct option is (b) False |
|