1.

For frog filling, for use of cut bricks, for bonding, for uniform joints, wastages, etc. 50% extra mortar may be required.(a) True(b) FalseI have been asked this question in homework.My question is taken from Analysis of Rates of Cement Concrete in chapter Analysis of Rates of Civil Engineering Drawing

Answer» CORRECT choice is (b) False

Easiest explanation: For frog filling, for use of cut bricks, for bonding, for uniform JOINTS, wastages, etc. 15% extra mortar MAY be required.