| 1. |
In earthwork per 28.30 cu m, how many beldars and mzdoors are required per day?(a) 15 Beldars and 8 Mazdoors(b) 0 Beldars and 14 Mazdoors(c) 2 Beldars and 0 Mazdoors(d) 5 Beldars and 4 MazdoorsThis question was addressed to me in an internship interview.This key question is from Estimation of Basic Rates Occurred topic in division Analysis of Rates of Civil Engineering Drawing |
|
Answer» The correct option is (d) 5 Beldars and 4 Mazdoors |
|