1.

In flooring how many masons, beldars, mazdoors and bhishti per day are required?(a) 4 Beldars, 10 Mazdoors, 10 Masons and 8 Bhishti(b) 4 Beldars, 3 Mazdoors, 5 Masons and 1 Bhishti(c) 9 Beldars, 13 Mazdoors, 5 Masons and 1 Bhishti(d) 3 Mazdoors, 5 Masons and 10 BhishtiI got this question during an interview for a job.My doubt stems from Estimation of Basic Rates Occurred topic in chapter Analysis of Rates of Civil Engineering Drawing

Answer»

Right option is (b) 4 Beldars, 3 Mazdoors, 5 Masons and 1 Bhishti

Explanation: 4 cm thick cement concrete flooring of 40 sq m require-4 Beldars, 3 Mazdoors, 5 Masons and 1 Bhishti PER day for MIXING, LAYING and FINISHING.