In flooring how many masons, beldars, mazdoors and bhishti per day are required?(a) 4 Beldars, 10 Mazdoors, 10 Masons and 8 Bhishti(b) 4 Beldars, 3 Mazdoors, 5 Masons and 1 Bhishti(c) 9 Beldars, 13 Mazdoors, 5 Masons and 1 Bhishti(d) 3 Mazdoors, 5 Masons and 10 BhishtiI got this question during an interview for a job.My doubt stems from Estimation of Basic Rates Occurred topic in chapter Analysis of Rates of Civil Engineering Drawing |
|
Answer» Right option is (b) 4 Beldars, 3 Mazdoors, 5 Masons and 1 Bhishti |
|