________________ involves the preparation of tenders based on a typical or notional bill of quantities or schedule of works.(a) Framework tendering(b) Selective tendering(c) Negotiated tendering(d) Serial tenderingI have been asked this question in a job interview.This key question is from Contract System topic in division P.W.D of Civil Engineering Drawing

Answer»

Correct ANSWER is (d) Serial tendering

Best explanation: The RATES submitted can then be used to value works over a series of similar projects, often for a fixed PERIOD of time FOLLOWING which the tendering procedure may be repeated. Serial tendering can reduce tender costs, and may encourage suppliers to submit LOW rates to secure an ongoing program of work.