Laying cement concrete – 6beldars, 8 mazdoors, ¾ Bhishti and ¼ mason can do 2.83 cu m(100 cu ft) per day.(a) True(b) FalseThis question was addressed to me in an interview.My question is based upon Estimation of Basic Rates Occurred topic in section Analysis of Rates of Civil Engineering Drawing

Answer»

The correct answer is (B) False

For explanation I would say: LAYING cement CONCRETE2 beldars, 3 mazdoors, ¾ Bhishti and ¼ mason can do 2.83 cu m(100 cu ft) per day.