1.

Reinforced cement concrete work is usually estimated under ________ items.(a) two(b) three(c) four(d) oneI have been asked this question in semester exam.This question is from R.C.C. Work and Amount topic in section Different Type Roofs, R.C.C of Civil Engineering Drawing

Answer»

The CORRECT CHOICE is (a) two

The explanation is: The concrete work including centering and SHUTTERING, and BINDING of steel bars in position is taken under one item in cu m (cu ft) and the steel reinforcement and its bending is taken under one item in (cwt).