1.

In village planning the site should be selected near the existing village, it should be on elevated ground level.(a) True(b) FalseI had been asked this question by my school teacher while I was bunking the class.Asked question is from Planning in division Village Housing of Civil Engineering Drawing

Answer»

The correct answer is (a) True

The explanation is: To PREVENT it from flood it should be on elevated ground level. TOPOGRAPHY of ground should be such that proper drainage is POSSIBLE. Each VILLAGE should be SEPARATE unit having agricultural land surrounding the village.