| 1. |
Stabilized soil wall is cued for ______ to ______ days by sprinkling water.(a) 3 to 6(b) 15 to 20(c) 7 to 10(d) 20 to 35I had been asked this question in exam.Question is from Types of Construction and Specification topic in division Village Housing of Civil Engineering Drawing |
|
Answer» Correct option is (c) 7 to 10 |
|