The expected out turn of 2.5 cm cement concrete floor per manson per day?(a) 1.5 sq. m(b) 0.5 sq. m(c) 7.5 sq. m(d) 2.5 sq. mI got this question in a job interview.Enquiry is from Labour Rates for Workers in division Schedule of Rates Metric and F.B of Civil Engineering Drawing |
|
Answer» Correct answer is (c) 7.5 SQ. m |
|