The expected out turn of cement concrete for 1 : 2 : 4 per mason per day is 5.(a) True(b) FalseThe question was asked by my school teacher while I was bunking the class.My doubt stems from Labour Rates for Workers topic in chapter Schedule of Rates Metric and F.B of Civil Engineering Drawing

Answer»

Correct choice is (a) True

The explanation is: For 1 : 2 : 4 CONCRETE, 1m^3 need Labour constant.

Mixing concrete = 3.00 hour/m^3.

Lifting and carrying concrete = 1.20 hour/m^3.

Compacting concrete = 0.80 hour/m^3.

Levelling SURFACE of concrete = 0.10 hour/m^3.

Total= (3+1.2+0.8+0.1) = 5.