1.

A ____________ is defined as accomplishment in planning a project.(a) activity(b) event(c) schedule(d) planningThe question was posed to me during an internship interview.My doubt stems from Developing a Network in division Planning of Building and Colony of Civil Engineering Drawing

Answer» CORRECT OPTION is (b) EVENT

The best I can explain: The Event is RECOGNISABLE as a particular instant of time and not a passage of time and is represented by a geometrical figure such as circle, RECTANGLE, square, etc. Beginning and end of a job or number of jobs are events.